Ed Ferrentino's
BATH-IN-A-WEEK
guarantee boosts business
(Originally published in
Remodeling, April 1999)
When Ocala, Fla., remodeler Ed Ferrentino
tells potential clients that their peeling, leaking bathroom can be replaced
in a week, they often balk. "They ask, 'Are you sure?'" Ferrentino says.
He's sure. In fact, he guarantees it -
a
promise that helps him land the jobs he bids
on.
Seven or eight years ago, Ferrentino got the
process of replacing bathrooms in a week down to a science. Of course,
that's not every bathroom. Forget the ones where "we're moving walls or
reconfiguring space." he says.
Those he can do in a week tend to be in developments built a decade or more
ago, and many of his clients are seniors. "People have been in them 10 or 12
years and can't step up to the tubs anymore," he says. Typically, Ferrentino
takes out the tub, replacing it with a walk-in shower.
Planning begins several weeks before the job
starts, when the remodeler, having inspected the bathroom, agrees on a date
to begin construction. He usually starts about two weeks later. Once the
date's set, Ferrentino calls his plumber, so he can be there immediately
after demolition to replace pipes or anything else that requires a plumbing
license. He also contacts his suppliers and sets a date for delivery and
installation. "All the material is in our possession before we start,"
Ferrentino says. Components are standardized in the company computer and
usually vary only by size and color. Ferrentino's crew will do everything
but the plumbing, electrical, and tub or shower installation. Once the
footwork is completed, the week's work goes something like this:
MONDAY: Start demolition. "We've got it
gutted by 10 or 12," Ferrentino says. Once the fixtures are out, the plumber
comes in to install new valves or pipes, or, if a shower's going in, he
installs the shower pan. When the plumber is through, the crew hangs
drywall. By the end of the day, "if we're really lucky, we've got the first
coat of mud on the rock."
TUESDAY: Finish the drywall.
WEDNESDAY: This is the marble man's day.
Ferrentino often replaces an old tub or shower with a cultured marble tub or
shower surround. "We make the marble panels 3 or 4 inches bigger than we
need, then cut to fit," he says. The marble fixture manufacturer delivers
the product on its own truck. Ferrentino favors the one-piece molded marble
pan because "it can't leak. I've done two conventional shower pans," he
says, "and had to replace them both." Ferrentino has the manufacturer
install both the marble shower and any glass that goes into it, such as a
shower door. He does so for two reasons: "It's fairly heavy," Ferrentino
says, and "the breakage factor."
THURSDAY: Painting, flooring, setting the
vanity.
FRIDAY: Re-install the commode, along with
the sink faucets and shower valves. At this point, the plumber may have to
make a return trip.
SATURDAY: Wipe down the floors, polish the
fixtures, peel the labels off the marble, and turn it over to the homeowner.
"Oh, and pick up my check," Ferrentino adds. Ferrentino points out that the
key to turning around a faceted thinking. "My dad taught me to build it in
my mind first," the remodeler says, "from digging the footers to putting the
key in the front door." Planning and scheduling weeks in advance are more
critical than ever due to the current volume of work in northern Florida.
"Up until this year, you could call a subcontractor or supplier and get him
there on a day's notice," he points out. Now, "we're feasting on jobs."
When similar bathrooms take two or three weeks to complete, Ferrentino says,
it's because the contractor doesn't call subs or suppliers until he himself
starts tearing out the old fixtures. Ferrentino's cookie cutter bathroom
comes with a standard price: $7,500. Five years ago, bathrooms accounted for
between 8 percent and 10 percent of Ferrentino's business. Last year, 24.8
percent of his $1 million annual revenues came from bathroom replacements.
The quick turnaround sways potential clients who have "heard the horror
stores of bathroom replacements that took two or three weeks, with the room
torn up and nothing done for days on end," Ferrentino says. "We guarantee
them we'll be done on Friday, barring no unforeseen circumstances."
And those, of course, do happen. Once a marble
shower surround cracked while being unloaded off a truck. Sometimes rotted
out floor underlayment or studs have to be replaced. Recently, the
contractor pulled down the tile in a shower he was replacing to discover
there was nothing behind the tile but grout, and nothing behind the grout
but dirt. Ferrentino has a policy of personally looking at every bathroom
before signing the contract. If he determines it can be done in a week, he
promises that it will be. But that's not in writing. "We back it up with our
reputation," he says.
|