How Long Does it Take to Get a Permit in Ocala, FL - and What is the Process?

At Ferrentino & Son Construction, we know how important it is to stay on schedule with your home improvement or construction project. One of the most common questions we hear from our clients is: “How long does it take to get a permit in Ocala, Florida?” The answer depends on a few factors: like the type of work, the complexity of the project, and how complete your application is. Here’s a breakdown of what you can expect and how the process works.

Why Permits Matter in Ocala, FL…

Building permits are legally required for many types of residential and commercial work in Ocala and Marion County. Whether you're adding a new structure, remodeling, installing a fence, or doing electrical or plumbing work, a permit ensures your project complies with local building codes and safety standards. You can access Marion County Building Safety through their web portal.

Here’s how the typical permitting process works in Ocala:

1. Determine the Type of Permit You Need

Common permit types include:

  • Building (for structural changes, additions, garages, etc.)

  • Electrical

  • Plumbing

  • Mechanical (HVAC)

  • Roofing

  • Fence or driveway

You can verify which permit you need by contacting the City of Ocala Building Department or visiting their website.


2. Prepare Your Plans and Documents

For most permits, you’ll need:

  • A detailed scope of work

  • Site plan or survey

  • Construction drawings (may require a licensed engineer or architect)

  • Contractor information

  • Any necessary product approvals


3. Submit the Application

You can submit permits online through the City of Ocala Citizen Access Portal or in person at the Ocala Growth Management office.


4. Plan Review

Once submitted, your application goes into review. This includes:

  • Zoning Review

  • Building Code Compliance

  • Engineering and Utility Review (if applicable)

This part can take anywhere from 5 to 15 business days for standard residential permits. More complex or commercial projects may take longer. It can take up to 30 days or more.


5. Revisions (if needed)

If the city finds any issues, they’ll send comments back to you or your contractor. You’ll need to make corrections and resubmit for approval.


6. Permit Issuance

Once everything is approved, you’ll receive your permit. Work can legally begin once the permit is posted onsite.

How Long Does It Really Take?

Permit Type Estimated Time (Business Days)

Minor Residential (fence, window, roof) 1–5 days

Standard Residential Remodel/Add-on 5–15 days

New Home Construction 10–30 days

Commercial Projects 15–30+ days

Can You Speed Up the Process?

Yes, here are a few tips:

  • Hire a licensed contractor (like Ferrentino & Son) who knows the local process.

  • Submit complete and accurate plans to avoid delays.

  • Respond to correction comments quickly.

  • Check for HOA approvals in advance, if applicable.

Let Ferrentino & Son Handle It for You

Permitting can feel like a hassle, but it doesn’t have to be. At Ferrentino & Son, we handle the entire process for you, from preparing your plans to submitting the paperwork and pulling the permits. That way, you can focus on the exciting part: seeing your project come to life.

If you have questions about permitting in Ocala or want to get started on your next home improvement project, Contact us today!